Reconstruction of Metallurg Stadium, Kryvyi Rih city

  • Performing reinforcement for pouring monolithic slab foundation western stands; ▴ installation and reinforcement of ditches for tower cranes is carried out;
  • ditches are installed under the north and south stands, as well as under lighting masts;
  • dismantling works are underway in the interior of the east stand.

Start of works: January 2021